ElkConstruct
ElkConstruct
Back to Blog
Industry

Why 73% of Construction Projects Go Over Budget

SC
Sarah Chen
February 6, 2025
5 min read

A 2024 study by McKinsey & Company found that 73% of commercial construction projects exceed their original budget, with an average overrun of 16.3%. Large infrastructure projects fare even worse, with overruns frequently exceeding 30%. These numbers have remained stubbornly consistent for decades despite advances in project management methodology. Understanding why requires looking beyond simple explanations.

The most significant driver of cost overruns is incomplete scope definition at the estimating stage. When estimators miss items or undercount quantities, the resulting budget gap doesn't surface until construction is underway. By then, the contractor is committed and the costs are real. Research from the Construction Industry Institute found that projects with poor scope definition at the front end are 50% more likely to experience major cost overruns compared to projects with thorough preconstruction processes.

Design changes during construction represent the second largest contributor. The average commercial project experiences 35 to 50 change orders, and each one carries direct costs plus ripple effects on schedule and labor productivity. While some changes are unavoidable, many stem from insufficient coordination between design disciplines during the preconstruction phase. Clashes between architectural, structural, and MEP systems that should have been caught in design review instead surface during installation.

Labor productivity assumptions also play a critical role. Most estimating databases use national average productivity rates, but actual field productivity varies enormously based on project complexity, site conditions, workforce experience, and weather. A concrete crew might achieve 95% of book rate on a straightforward slab-on-grade but only 60% on a complex elevated deck with extensive embeds and blockouts.

Material price volatility has intensified the problem in recent years. Lumber prices swung by over 300% between 2020 and 2023. Steel, copper, and PVC have all seen significant fluctuations. Estimates built with pricing that is even 60 days old can be materially inaccurate by the time construction begins.

Supply chain delays compound cost overruns by extending project durations. Every additional month on a project adds general conditions costs: superintendent salaries, trailer rental, temporary utilities, insurance, and equipment. These time-dependent costs are often underestimated in original budgets.

Technology is beginning to address these root causes. AI-powered estimating tools reduce scope gaps by systematically analyzing drawings. BIM coordination catches design conflicts before they reach the field. Real-time material pricing databases keep estimates current. Predictive analytics flag schedule risks early enough to mitigate them. While no tool eliminates overruns entirely, the combination of better data, smarter analysis, and faster iteration is measurably narrowing the gap between estimated and actual costs.

cost overrunsbudgetingconstruction managementindustry data
SC

Sarah Chen

Content Lead